R.E. Shaw Building Project

Thank you Town of Millbury for Approving the New R.E. Shaw Elementary School!

Estimated Project Bid Date: December 2020

Construction of New School Begins: April 2021 – July 2022

Teachers Move-In: July 2022

Demolition of Existing Shaw School: July 2022-August 2022

Start of the School Year in the new Shaw School: September 2022

Construction of New Athletic Fields: September 2022 – December 2022

Repaving of entrance driveway: July 2023

The Millbury Public School District has received approval from the Massachusetts School Building Authority (MSBA) to design a new grades 3 – 6 school facility for a certified enrollment of 550 students at 58 Elmwood Street (the site of the current Shaw School) . The MSBA has agreed to contribute between 24.2 to 24.7 million dollars of the project costs.

Carousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel imageCarousel image

Fast Facts about the New R.E. Shaw Building Project

Building Square Footage: 90,266

(Current school: 76,437 sf)

Grades: 3-6

(Current school: Gr. 4-6)

Estimated LEED Platinum Certified Building Systems

(the highest LEED rating achievable)

STEM-focused learning spaces with new technology infrastructure

Building design that maximizes student and staff safety

Total Estimated Project Cost: $60,922,761

(includes design, construction, furniture and technology)

Anticipated Maximum Massachusetts School Building Authority (MSBA) Share: $25,002,981

Anticipated Maximum Town Share: $35,919,780

Based on a $36 million bond for 30 years at a 3.75% fixed interest rate, the expected tax impact will be $1.21 per $1,000 assessed value.

Visit the FAQ and Documents pages for more facts about the Shaw Building Project