Timelines
Project Design Schedule
Project Design Schedule
Massachusetts School Building Authority (MSBA) Project Process Timeline
Massachusetts School Building Authority (MSBA) Project Process Timeline
Process Overview Summary.pdf
Start to Finish Process Timeline
Start to Finish Process Timeline
start to finish process.pdf
Design Milestones
Design Milestones
June 22, 2020
60% Construction Documents to Building Inspector to Review
August 3, 2020
60% Construction Documents submission to the MSBA
November 6, 2020
90% Construction Documents submission to the MSBA
December 14, 2020
100% Construction Documents submission to the MSBA
Construction Schedule
Construction Schedule
April 2021 – July 2022
Construction of new school
July 2022
Teachers move-in
July 2022-August 2022
Demolition of existing Shaw School
September 2022
Start of the school year in the new Shaw School!
September 2022 – December 2022
Construction of new athletic fields
July 2023
Repaving of entrance driveway